SAP Message REXCJP335 - Start or end reading missing for meter & assigned to & for period &

Diagnosis
Start or end meter reading missing for the selected meter and period.

Procedure
Interpretation of the measurement documents for the service chargesettlement with fix unit prices in Japan:

  • The first measurement document defined for a day shows the final meter
  • reading on the day before the date of the measurement document.
    • Additional measurement documents defined for a day show the meter
    • readings on the day of the measurement documents.
      Example:
      For a meter, there are the following measurement documents:
      • 31.12.2005,, 0,000,,kWh,,( shows the consumption till 30.12.2005 )

      • 31.01.2006,,1000,000,,kWh,,( shows the consumption between 31.12.2005 -
      • 30.01.2006 )
        • 28.02.2006,,1000,000,,kWh,,( shows the consumption between 31.01.2006 -
        • 27.02.2006 )
          For the period 01.01.2006 - 31.01.2006, the consumption will be in thiscase: 1003 kWh.
          ( 30 day * 1000 kWh / 31 day + 1 day * 1000 kWh / 28 day = 1003 kWh )

1036317Message long texts