SAP Message KV165 - No target costs in target cost version & - missing plan for & &

Diagnosis
In target cost version &v1&, notarget costs could be calculated for &v2& &v3&from the planned costs for one of thefollowing reasons:

  • No cost elements have been planned

  • No activity quantity has been planned
  • System Response
    The lack of target costs means that:

    • No target costs can be shown in the report

    • The variance calculation process
    • cannot calculate differentiated variances

      Procedure
      Plan the cost elements and activity types for the cost center.
      Proceed
      Calculate the variances again. If you are working in reporting, selecta report that does not require target costs.

432127KSS2: Cost element group in target cost version