SAP Message KV154 - No standard cost estimate for material & in plant & on &

Diagnosis
You are using a function that calculates thetarget costs in the currentstandard cost estimate for thematerial. Using this information, the system can calculate thefollowing data:

  • Work in process (WIP) for the confirmed
  • WIP quantities
    • Scrap for the confirmed scrap quantities

    • Variances between the target costs and the
    • control costs
      However, the cost estimate for material &v1& in plant &v2& is:
      • Missing

      • Not released

      • Not valid on &v3&

      • Not saved as an itemization

      • Not valid at the time WIP or
      • variances were calculated
        • Not saved in the controlling area currency

        • This can be the case when the controlling area currency is not the sameas the company code currency. Since variances are always calculated inthe controlling area currency, the cost estimate must be saved incontrolling area currency (refer to "Procedure").
          The settlement type in the order determineswhen the cost estimate must be valid.
          • If cumulative variances are calculated (variances for the entire life
          • of the order), the cost estimate must be valid on the day of finaldelivery (status DLV) or, if no final delivery has taken place, on theday the order becomes technically completed (status TECO), or otherwiseon the day the order is entered.
            • If the variances are calculated by period, the cost estimate must be
            • valid on the last day of the period.
              If the target costs are calculated directly in a report, the costestimate must be valid on the last day of the reporting time frame.
              Note that you can only valuate work in process and scrap at targetcosts on the basis of a product cost estimate
              with quantity structure. It is not possible to valuate work inprocess and scrap using a unit cost estimate.

              System Response
              Because no target costs were calculated, the system cannot do thefollowing:

              • It cannot display a report on the target costs.

              • It cannot split the difference between the planned costs and the
              • control costs into different variancecategories when it calculates the variances.
                Instead, the difference is updated as aremaining variance only.
                • It cannot valuate the scrap and the work in process.
                • Procedure
                  If you want to calculate variances such asinput quantity variances orresource-usage variances, proceedas follows:
                  Check the validity period of the cost estimate.
                  Proceed
                  Check the costing view in the master record of the material beingmanufactured.
                  Proceed
                  If necessary, release the cost estimate for the material.
                  Proceed

                  • Create a new cost estimate for the material, and save the cost estimate
                  • in itemized form by turning on the Itemization field in theUpdate parameters dialog box.
                    Proceed
                    • Calculate the WIP or variances again.

                    • If you are working in reporting, select a report that does not refer tothe target costs.

152210Define flexible message types