SAP Message CC163 - Date & is within a protected time period

Diagnosis
You see this message in one of the following processing situations:

  • You are processing a change master record:

  • Entering the valid-from date
    Entering an alternative date
    Date shift of valid-from date or alternative date
    Assigning alternative date to change object or deleting an allocation
    • You are processing a change object with reference to a change number
    • whose valid-from date is in theprotected time period:
      Changing a change object (for example, BOM or routing)
      Assigning or changing a revision level

      System Response
      The system checks the control data for data shifts in Customizing forengineering change management. In your company, a protected time periodis defined.
      In the fields Warn. time in days and/or Error time in days
      , a number of calendar days defines how the protected time period iscalculated.

      Procedure
      If the message is:

      • A warning message, processing is allowed. However, we advise you to
      • check the change objects. If you confirm the warning message, you cancontinue processing.
        • An error message, processing is not allowed.

576387Error during filling with date check