SAP Message CACSRCP042 - Creation of worklist for commission case &1 terminated due to lock error

Diagnosis
The initial commission case could not be locked. It is probably beingprocessed by another user at the current time.

System Response
Processing of the initial commission case was canceled.

Procedure
The status of the initial commission case has not changed, althoughprocessing was canceled. Start preparation again later if the status isstill Ready to Create Worklist. If another user has carried outthe preparation, the status is Worklist Successfully Created. Inthis case, the worklist cannot be created again.