Diagnosis You have entered time contraints for the activity that have causeddiscrepancies in scheduling. The reasons could include:
- The time constraints for the predecessor or successor have either too
small or too large of an interval to each other and the duration of theactivity is not flexible.
- You have entered time constraints for the start and finish of the
activity that have too small or too large of an interval to each other.
- You have entered start and finish dates that are not correct, for
example, the time constraint for the finish date is before the timeconstraint for the start date.Procedure
- Check the time constraints for the activity.
- Check the basic dates for the network in the network header.
|