Diagnosis You have maintained a date constraint for the end of the activity. Backward scheduling has determined a latest date which is before theconstraint. Procedure INCLUDE 'NA_ALLG_MOEGLICH' OBJECT DOKU ID TX
- Check the date constraint of the activity.
- Check the basic dates of the network in the network header.
|