Diagnosis WBS element &V1& is not defined as a billingelement>. This being the case, you cannot plan revenues in it.System Response Processing stopped. Procedure
- Correct your input by entering a WBS element which is defined as a
billing element.
- If you want to plan revenues in WBS element &V1&, the system
administrator or some other authorized person, such as the projectmanager, must flag it as a billing element.Action by system administrator Flag WBS element &V1& as a billing element. RESET N2 In the Project System, go to the "Operative Structures" menu Choose Project struct -> Change. Enter the project definition and press ENTER. Choose Goto -> WBS element overview -> Operative indicators Define the billing elements.
|