SAP Message BP025 - Define planning elements

Diagnosis
The plan profile assigned to the project only allowscost planning in WBS elements which are defined as planning elements.
You can only carry out planning if you have defined planning elementsor have maintained a plan profile that allows planning on all WBSelements.

System Response
Processing stopped.

Procedure
You have two options:

  • define planning elements for your project

  • RESET N2
    In the "Project Management" menu, choose Master data -> Work breakdownstructure -> Change.
    Enter a project definition and press Enter
    Choose Goto -> WBS elem.overview - Operative inds
    Define the planning elements you need
    • Have your system administrator or some other person authorized to
    • configure the Project System do this.

      Action by system administrator:
      In the project profile, authorize cost planning in all WBS elements