SAP Message BP024 - Planning permitted in planning elements only

Diagnosis
In the Project System configuration menu, the system manager or anotherauthorized person can use the plan profile to determine whethercost planning is possible in allWBS elements or only on thosedesignated as planning elements.
The plan profile for your project stipulates that cost planning is onlypossible in planning elements.

System Response
Processing stopped.

Procedure
You have two possible courses of action:

  • You must define planning elements for your project.

  • RESET N2
    To do this, choose Project management -> Master data -> Work breakdownstruc -> Change.
    Enter a project definition and press ENTER.
    Choose Goto -> WBS element overview -> Operative indicators.
    Define your planning elements
    • Ask your system manager or some other person authorized to maintain the
    • configuration menu.

      Action by system manager
      In the plan profile, stipulate that cost planning is permitted in allWBS elements.
      IF &DEVICE& = 'SCREEN'
      Proceed
      ENDIF