SAP Message BK143 - Cost center &/activ. type & is not yet planned in version &/&

Diagnosis
Planning was not carried out for the given combination of cost centerV1/activity type v2 in fiscal year v4 for version v3
Because, in addition, no actual activity price indicator was determinedfor activity type &V2&, no actual allocation can be carried out forcost center &V1&/activity type &V2&.

Procedure
To allocate the activity type in actual, either

  • carry out activity type planning for the given combination

  • set the actual activity price indicator for activity type &V2& so that
  • a follow-up valuation is carried out in actual
    Planning and maintenance of the activity price indicator is undertakenin CCA with the function "Activity type planning".