SAP Message AP157 - Budget categories are assigned to a total of &%

Diagnosis
You entered a percentage rate for each budget category. This percentagerate is used later in reporting to determine how much of the planvalues and budget values of the measure should be assigned to the givenbudget categories. The total of these percentages should be 100%.However, the total was &V1&%.

Procedure
Check your entries.
The total of the percentages assigned is not allowed to exceed 100%. Atotal of less than 100% is permitted.
You do not need to assign percentage rates to the budget categories atall in the following example:
Plan values and budget values do not have any meaning for you inreporting, because you want to check the actual values against theprogram budgets, but do not want to check them against the measurebudgets.
When this applies to you, you do not have to set percentage rates forbudget categories at all.