Diagnosis Implementation start date &V1& that was entered is after the completiondate &V2& of variant &V3&. The implementation start date always has tobe before the completion date (&V2&). System Response The entry is not allowed. Procedure Do one of the following:
- Correct implementation start date &V1& that you entered so that it is
before or the same date as completion date &V2&.
- Correct completion date &V2&, so that it is after or the same date as
implementation start date &V1&.
|