SAP Message AO018 - Co. code currency &1 was adopted, since differnt CO area currency allowed

Diagnosis
In controlling area &V2&, the company code currency is allowed todiffer from the controlling area currency. Therefore, the appropriationrequest currency (object currency) always has to be the same as thecompany code currency.
However, this is not the case.

Note
At the present time, it is not possible to plan on the appropriationrequest in object currency. However, it is possible on the measures(WBS element or order) that are created from the appropriation request.

System Response
The system automatically adopts company code currency &V1& as theobject currency of the appropriation request.

Procedure
Check if the adoption of company code currency &V1& is correct. Alsocheck the company code you entered.