Diagnosis According to the scheduling levels in Customizing, no scheduling isallowed for this order/these orders. Procedure The scheduling levels (detailed, prod.rate, rough-cut) are maintainedin Customizing in the MRP menu. They depend on:
- the order group (here: "planned order"),
- the order type of the planned order as well as,
- the production scheduler, that must be allocated in the material
master. The indicator for scheduling must also be selected for the chosenscheduling level.
|