| DiagnosisIntegrated planning is not active. This must be active to be able toupdate contract values, planned revenues or planned costs.
 Integrated planning is active if indicator Integrated Planning>is set for both the WBS element and the CO version.
 Procedure
 You can set the indicator for the WBS element.Call the Project Builder >(transaction CJ20N).
 In the tree structure, select WBS element &V1&.
 Select tab page Control>.
 Set indicator Integrated Planning>.
 Save data.
 
 You can also set the indicator Integrated Planning> in theproject profile. In Customizing for  Project System > select IMGactivity Activate Integrate Planning forWBS Elements>. This indicator will then be automatically transferredfor all WBS elements for which you selected this project profile.
 |