Solution : https://service.sap.com/sap/support/notes/318412 (Connexion à SAP Service Marketplace requise)
Mots Clés : 
additional key words co11, correction report zkbedrep, existing capacity requirements, capacity requirements, program correction, iw41capacity requirements, require confirmation, finally confirmed, operation elements, program error
Notes associées : 
       
| 197669 | Capacity requirements despite of final confirmation | 
| 155694 | IW45: Cancel confirmation WRONG_PARAMETERS | 
| 152706 | Incor.cap.reqmts for partially confirmed activities | 
| 148632 | Incorrect results in capacity requirements planning | 
| 141688 | CN25: No capacity reduction through confirmation | 
| 130821 | Cap. reqmnts f. TECO network activity reconstructed | 
| 119518 | No rdction of rough-cut plnning+rate-basd capacties | 
| 85896 | Confirmation sets up capacity requirements again |